Friday, May 29, 2026

RAND: "How Much More Power Can the U.S. Grid Provide for AI?"

It turns out that more is possible.*

From the RAND Corporation, April 20:

Projections and Policy Implications for 2030 

Key Findings

  • There are plans to add a total of 151 gigawatts (GW) of front-of-the-meter (FTM) and 149 GW of behind-the-meter (BTM) nameplate capacity by 2030. After project completion rates, retirements, and resource reliability are accounted for, these additions translate into approximately 82 GW of additional net available capacity — about 33 GW from FTM resources and 49 GW from BTM resources that reduce peak grid demand.
  • Most planned FTM additions are concentrated in the Electric Reliability Council of Texas (ERCOT), while BTM capacity is more evenly distributed across ERCOT, the Midcontinent Independent System Operator, and regions without centralized market operators.

The anticipated growth in electricity demand from artificial intelligence (AI) is large, rapid, and geographically concentrated. Because of uncertainty about which planned generation projects will be completed, it is difficult to assess whether future U.S. grid capacity will keep pace with demand from AI data centers. An additional challenge lies in translating announced nameplate capacity into comparable estimates of reliable power that can meet large, inflexible loads to support data center power needs.[1]

These factors complicate efforts to estimate how much additional power capacity the United States is likely to have by 2030.

Estimating Additional Power Capacity

A team of RAND researchers estimated how much additional power capacity the United States is likely to have by 2030 by translating planned electricity supply resources into a common measure of reliable capacity. For front-of-the-meter (FTM) resources,[2]

the researchers analyzed planned generation and storage projects based on independent system operator (ISO) interconnection queues and federal generation data and applied historical completion rates by region and technology.[3] This process adjusted for resource contributions to reliability and accounted for planned retirements to estimate net additions to grid capacity.

For behind-the-meter (BTM) resources,[4]

such as customer-sited solar and battery storage, the researchers relied on national deployment projections through 2030 and converted projected nameplate capacity into effective capacity using the same framework as in FTM.[5] Using this approach, the researchers estimated how much BTM resources could reduce peak grid demand and free up capacity for large loads, such as AI data centers.

Estimates of Front-of-the-Meter and Behind-the-Meter Net Availability Capacity

The researchers found that the United States could add approximately 82 gigawatts (GW) of net available capacity by 2030,[6]

consisting of 33 GW from FTM resources and 49 GW from BTM resources; see Table 1.

Table 1. Front-of-the-Meter and Behind-the-Meter Available Capacity Additions by Region, 2025–2030 (GW)

Region FTM BTM Combined
CAISO (1.2) 3.6 1.9
ERCOT 59.0 10.0 69.0
NE-ISO 3.3 1.0 4.3
MISO (12.0) 11.0 (0.8)
NY-ISO 0.4 3.3 3.6
PJM (5.3) 4.7 (0.7)
SPP (1.7) 3.5 1.8
All other regions (9.4) 12.0 2.7
Total 33.0 49.0 82.0

NOTE: CAISO = California Independent System Operator; ERCOT = Electric Reliability Council of Texas; MISO = Midcontinent Independent System Operator; NE-ISO = New England Independent System Operator; NY-ISO = New York Independent System Operator; SPP = Southwest Power Pool. Negative FTM values (shown in parentheses) indicate that the expected additions to available capacity are less than the reductions in available capacity from expected retirements. Numbers might not add up to totals because of rounding.

Figure 1 illustrates how planned FTM generation and storage projects are translated from 1,086 GW of nameplate capacity into the estimated 33 GW of net available capacity after project attrition, retirements of existing plants, and differences in resource contributions to reliability are accounted for.

Figure 1. Method to Translate Planned Front-of-the-Meter Projects to Data Center Power Need

....MUCH MORE 
*One of the keys is looking at and really understanding the system as built and then being brutally honest with ourselves about what we've learned