The first excuse for being grumpy is both GEV and PWR being grouped (subsumed?) with Fermi under the umbrella "AI." The second after the jump. 

From Barron's December 12:

Fermi Stock Heads for Worst Day on Record as AI-Energy Company Loses Funding Commitment From First Major Tenant

Fermi stock plunged on Friday after the energy and real estate company said a $150 million funding deal with one of its power grid’s potential tenants had fallen through.

Fermi has been continuing site work at Project Matador, a Texas-based grid that it said will supply 11 gigawatts of power to the massive data centers that power artificial intelligence.

However, the project appears to have hit a snag. Fermi disclosed in a securities filing Friday that it had lost a funding commitment from a potential tenant earlier this week.

On Sept. 19, the company entered into a nonbinding letter of intent with what it called an investment-grade rated tenant to lease part of the Project Matador site. The parties entered into a subsequent agreement in November, with the tenant agreeing to advance up to $150 million to fund construction costs. No funds were drawn under the agreement.

The exclusivity period provided in the letter of intent expired on Dec. 9. Two days later, the tenant notified Fermi that it was terminating the November agreement for the $150 million funding commitment.

In spite of this development, “the parties continue to negotiate the terms of a lease agreement at Project Matador pursuant to the letter of intent,” Fermi wrote in the filing.

The company asserted it was “confident” it could meet the expected power delivery schedule at Project Matador, “as the demand for behind-the-meter power for AI remains robust over the near and long term.”

Fermi shares cratered 30% to $10.68 on Friday, putting them on pace for their largest single-day percentage drop on record as well as a record closing low, according to Dow Jones Market Data. The stock began trading on the Nasdaq and the London Stock Exchange through a simultaneous dual listing in October.

Evercore ISI analyst Nicholas Amicucci noted that the November agreement “validated a certain level of commitment from Fermi’s potential first tenant.” Its termination calls into question the letter of intent, he said.

“We continue to believe in the scarcity value of an electron,” Amicucci wrote, referring to power. “However, we would be naïve to believe shares would not be negatively impacted by this announcement.”....

....MUCH MORE 

At one point the stock was down over 50% on the day.

And the other reason I am grumpy? October 1:

"Fermi IPO Is a Risky Bet on AI Power. The Stock Is Soaring in Its Debut." (FRMI)

...Reiterating our long-held (and expensively gained) thinking on short selling:
In a bull market do not make shorts based on valuation, only short frauds, and even then be aware it may take years for the fraud to become apparent to the wider market and/or the short-seller is diagnosed as delusional.
 
In a bear market: "Short 'em all!"
 
There should be some opportunity to do the latter in 2026....
Like Mark Twain's cat, having been burned too many times on valuation shorts in a bull market we don't go near them. Okay, Twain's cat wasn't a short-seller, she once sat on a hot stove and in Twain's telling she'd never do that again. She also wouldn't sit on a cold stove.
 
The one positive I can glean from all this is that I will be able to drop the "...scarcity value of an electron" line into casual conversation.

Earlier on Fermi, June 28:

"A proposal for four nuclear reactors and 18 million square feet of data-center buildings near Amarillo aims to 'Make America Nuclear Again.'”

The WaPo headline is "Rick Perry’s AI plan: A colossal nuclear campus in Trump’s image" which, on first encounter I took to mean the campus was going to resemble President Trump's profile in silhouette. Now that would be weird. And would probably get federal funding.

From the Washington Post, June 26:

A company led by former energy secretary and Texas governor Rick Perry has submitted a federal application to build a nuclear power complex on what sponsors say would be the world’s largest data-center campus — a project with a distinctly political veneer.

Republican Perry is co-founder of Fermi America, a Texas company that has said it will soon announce details of its grand vision for a property next to the Pantex nuclear weapons plant near Amarillo. Its confidential application for construction of four one-gigawatt reactors, obtained by The Washington Post, says the expansive facility will be called the Donald J. Trump Advanced Energy and Intelligence Campus.

There are few proposals in the United States for new, full-size nuclear power plants, which are associated with cost overruns and long engineering delays. Many tech and energy companies are focusing their efforts on developing smaller, modular reactors that in theory can be built faster and more cheaply.

Fermi Executive Chairman Toby Neugebauer, a Texas private equity investor, said he’s confident the firm can build the nuclear complex by 2032, an extremely ambitious timeline. He argues that its remote Texas Panhandle location will speed permitting and construction.

“If you can’t do it here, you can’t do it anywhere,” he said in an interview Thursday.

The complex will also include large natural gas plants, with pipelines in the area supplying so much of the fuel that company officials say they can eventually supply AI companies with 11 gigawatts of energy — an amount equivalent to that used by all of Manhattan — on gas alone, if the nuclear plans falter.

Crucial details of Fermi’s plans remain unclear, including the specific financial backing Perry and his partners have secured, making its viability difficult to judge at this early stage. Fermi is partnering with the Texas Tech University system on the project, and the company’s founders include Perry’s son, Griffin, an investor who also sits on the board of the Cotton Bowl Athletic Association, sponsor of the annual college football game. The company says its roster of executives will include experts who have helped finance and build large power projects around the world, including nuclear plants.

Fermi America social media postings frame the unusual project as an homage to Trump, who named Perry energy secretary during his first term and who is taking steps to weaken the independence of the Nuclear Regulatory Commission (NRC) and give the White House more sway over nuclear energy approvals.

“It’s time we lead the charge to Make America Nuclear Again,” says a post on Fermi’s LinkedIn page, complemented with video of Trump turning his head stoically toward the camera. The White House did not respond to questions about the plan.

Fermi said it has not decided on a final name for the site, notwithstanding its use of the Trump moniker in its regulatory filings. The company says that it hopes to start construction on the nuclear plant next year and that it will have a large amount of gas power available for data centers on its campus by 2026.

The effort is among a variety of gargantuan data-center projects that are on the drawing board or being built in the U.S.

Fermi on its website features a quote from Perry promising a Texas-scale operation: “At Fermi America, we’re really not interested in building the second largest energy driven data center in the world, we’re gonna build the largest.”

Officials at the NRC confirmed the authenticity of Fermi’s licensing application, which they said will be posted publicly in the near future.

Fermi’s June 17 cover letter to the NRC says the company is seeking an expedited approval process, filing the application in phases “rather than to wait for all the information that may be ultimately required to come in.”

The application says each of the Westinghouse AP1000 nuclear reactors also will be named individually after the current White House occupant. Most experts say building a nuclear plant of the size Fermi is proposing could take roughly a decade....

....MUCH MORE 

https://encrypted-tbn0.gstatic.com/images?q=tbn:ANd9GcSnA7I6Rqvwlzhv7TYVlVP-fqViMBg_tFVoVA&s 

Probably not related, June 27 - "Trump plans executive orders to power AI growth in race with China" (PWR; GEV; CCJ)