Key Takeaways
- GE Vernova fell 10% today, with Vistra and Constellation Energy, after Democrats won both chambers of Congress.
- Only about 20% of GE Vernova’s contracted gas turbine capacity serves data centers.
- Eaton and Caterpillar just reported rising data center demand, and new curbs would face a presidential veto.
- Next up: whether GE Vernova’s gas contracts reach the 130 gigawatts management expects by year-end.
GE Vernova (GEV) fell 10% this morning after Democrats won the Senate and the House in Tuesday’s midterms, and investors sold AI power stocks.
Vistra (VST) fell 12% and Constellation Energy (CEG) fell 7%. Yet Eaton (ETN) and Caterpillar (CAT) are still seeing data center growth.
Evercore ISI analysts led by Amit Daryanani wrote in a note: “Assuming a more restrictive data center development environment, this could create incrementally more negative sentiment for AI infrastructure exposed names.”
Sentiment is the key word here.
Most of these turbines aren’t for data centers
GE Vernova had 122 gigawatts of gas equipment under contract at the end of September. As of midyear, only about 20% of its contracted gigawatts served data centers....
....MUCH MORE